SAVANNAH, Ga. — The Port of Savannah handled 565,366 twenty-foot equivalent units (TEUs) in October, a 25% increase from October 2025, according to the Georgia Ports Authority. The total was the port’s second-highest monthly container volume on record.

The authority reported 160 vessel calls during the month, up 5% from a year earlier. Fiscal year 2027 volumes to date were up 7.8%, or 152,991 TEUs. WTOC reported the figures, which were also reported by the Statesboro Herald.

What Georgia Ports Said Drove The Increase

Georgia Ports Authority CEO Griff Lynch attributed the container volume to consumer spending, an extended peak shipping season and the port’s infrastructure. Authority President Kevin Price said some ocean carriers are returning to routes through the Suez Canal, which can shorten transit times to Savannah by 10 to 12 days.

The authority said the Ocean Terminal renovation in Savannah is more than 60% complete. The $1.6 billion project is expected to increase the terminal’s capacity from 200,000 TEUs to 1.75 million TEUs.

Planned Savannah Container Terminal

A large vessel carrying several raised container cranes moves along a river beside a wooded shoreline
A large vessel carrying several raised container cranes moves along a river beside a wooded shoreline. Photo: U.S. Army Corps of Engineers Savannah District · Public domain · resized. Image resized as needed and converted to WebP.

Georgia Ports Authority said the U.S. Army Corps of Engineers approved a permit for the planned Savannah Container Terminal, a $2.3 billion project. Construction is expected to begin in 2028. The terminal is planned to add capacity for 3.5 million TEUs.

The new terminal and current Ocean Terminal renovation are part of the authority’s planned capacity expansion in Savannah. DataPortuaria also reported the October volume and the port authority’s expansion plans.

October Cargo At The Port Of Brunswick

At the Port of Brunswick, roll-on/roll-off cargo, which includes vehicles and heavy machinery, totaled 69,599 units in October, down 3.6% from the same month last year. Heavy machinery cargo increased 25.8%, from 4,127 units in October 2025 to 5,193 last month, according to Georgia Ports Authority.

A fourth berth is under construction at Brunswick’s Colonel’s Island facility and is expected to open in November 2027, the authority said. The October port figures and construction update were also reported by WTOC.